In this work, Linear Programming Problems have been implemented to build four linear models for projects management. An Interior – Point Method has been implemented to solve such linear models, instead of using the usual techniques "Simplex Method", by implementing the "what's Best 9.0 " software, and obtaining the critical path in minimum completion time, minimum crashing cost and optimal total ( direct & indirect ) costs for a simple real project. Then we are verified the results obtained by implementing " Project 2000 " software to construct the project network and obtain the same critical path. Finally, the Programming Evaluation Review Technique (PERT) has been used, to find the probabilities of completing the project.
Linear Programming Techniques for Network Project Management